Hi

We have issue where commitment is not getting populated correctly in F41021 "Committed" column.

Commitment is controlled thru Manufacturing Constants which is soft/hard when print. For some reason in some of the cases commitment is not getting populated correctly in F41021 but F3111 still shows commitment. We are using 9.1.

for example if i generate 8 WOs of single parent item with same order quantity ,after WO processing thru R31410 partlist got attached with soft commit and after WO print partlist got hard committed.

issue is there is a child item whose required qty is 810 in single WO ,so in all eight WOs total required qty will be 6480 which is hard committed from same location and lot number (verified in F3111 table) but in F41021 for child item... "

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center