Prepayment - Project/Receivables
Dears,
I have done all the below points :
Go to Projects responsibility
Create a Contract Project.
Go to Billing Information-->Billing Setup.
"Date Effective Funds Consumption" Enable this flag to auto apply the receipt once the invoice is interfaced to AR.
Create an Agreement and Baseline Funding.
Go to Receivables responsibility.
Receipts-->Receipts
Create a Receipt.
Click on Apply
Select Apply to as - "On Account"
Apply and Save Changes.
Go to Projects module
Query the agreement created.
Click on Apply Receipt
Select the receipt created in AR.
Apply and save changes.
Create an Event with Bill Amount.
Run PRC : Generate Draft Invoice for Single Project.