Hard allocation at WO print

edited Oct 19, 2017 5:00AM in Manufacturing - JDE1 (MOSC) 5 commentsAnswered

In the mfg constants I have the commitment set to Soft, Hard at Work Order Print.

The commitment method on the components in the parts list is set to 'Lot Date'.

The Parts List processing option is set to blank - 'perform commitment processing....'

The components on the parts list have available inventory.

When I run the Work Order print (R31410 and R31415), no commitments are done.