Logic to create Work Pattern in Resource Requirement

edited Nov 1, 2017 5:00AM in Projects - EBS (MOSC) 1 commentAnswered

Hello,

Does anybody know the logic Oracle eBS uses to create the Work Pattern within the Resource Requirement when it's created from an assignment in the Workplan?

We did a couple of calculations but are unable to determine the logic. See the below table and Excel output

eBS

Our Calculation

 

19,0063,4622,00111,9821,00112,1419,0097,84
SeptemberHoursOktoberHoursNovemberHoursDecemberHours
Friday1-sep3,341-dec5,09
Saturday2-sep 2-dec
Sunday3-sep 1-okt 3-dec
Monday4-sep3,342-okt5,094-dec5,09
Tuesday5-sep3,343-okt5,095-dec5,09
Wednesday6-sep3,344-okt5,091-nov5,346-dec5,09
Thursday7-sep3,345-okt5,092-nov5,347-dec5,09
Friday8-sep3,346-okt5,093-nov5,348-dec5,09
Saturday9-sep 7-okt 4-nov 9-dec
Sunday10-sep 8-okt 5-nov

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center