RESOURCE USAGE NOT CHARGES IN BATCH IN INCREMENTAL BACKFLUSH

edited Nov 25, 2017 4:01AM in Process Manufacturing - EBS (MOSC) 1 commentAnswered

   AM USING INCREMENTAL BACKFLUSH AND IN FORMULA I USED CALCULATE STEP QUANTITY'S SET TO YES. IN RECIPE STEP MATERIAL ASSOCIATION HAS BEEN DEFINED.

MY ISSUE IS THAT WHEN I YIELD THE PRODUCT THROUGH INCREMENTAL BACKFLUSH RESOURCE USAGE ONLY DECODER TO THE STEPS IN WHICH WE HAD DEFINED STEP MATERIAL ASSOCIATION.

     MY SCENARIO IS GIVEN BELOW.

PRODUCT = 500 QUANTITY

FORMULA   500 QUANTITY

ROUTING STEPS

1 HEATING

2 FORMING

3 ANNEALING

4 QC

5 QA

IN STEP MATERIAL ASSOCIATION ALL INGREDIENTS ARE CHARGED TO FIRST STEP (HEATING) AND FISH GOODS ARE YIELDED AT QC STEPS . SO THE RESOURCE ARE ONLY CHARGES TO HEATING AND QC STEPS BUT I WANT IT SHOULD BE RECORDED IN ALL STEPS.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center