UMP MR Accomplishments
Just asking the question about Maintenance Requirement accomplishments.
I have a Maintenance Requirement that is due every 30 days. This maintenance for example was due on the 13th Oct 2017, however wasn't accomplished in the system until the 24th Oct 2017. However, the actual work was completed on the 16th Oct 2017. When the BUE was run it calculated that it was next due on the 23rd Nov 2017. This maintenance is due every 30 days and should be due on the 15th Nov 2017. We deferred the Maintenance Requirement using the counter name and Deferral To the correct day it should have been due. This worked as