Resource Percent Availability at task resource assignment
Hello,
Scenario:
While doing the resource assignment to the project a percent allocation say 50% allocation is done for the resource.
When I go to the project and open the resource plan its is correctly showing me duration as Partial, CM % as 50%. The weekly allocation too shows CP as 40.0 hrs and CM as 20.0 hrs. But when i try to assign resource to a particular task in WBS the Percent Availability Plan & Percent Availability Actual both show 100.
I want to know how the Percent Availability Plan & Actual are calculated, ideally percent availability plan for the project/task should have taken the CM% for that resource for availability % calculation.