I have an issue while defining PM Schedule, I need to reschedule Schedule Start dates whenever any manual work order for the same activity is created.

For Example:

I create PM Schedule for an activity for a fixed interval of 15 days.

Forecast Window showing work orders dates as follows:

1-JAN-17

16-JAN-17

31-JAN-17

Now if any work order is created on 10-JAN-17, it should reschedule next work orders schedule start dates

after 10-JAN-17, Next work order schedule start date should be 26-JAN-17, 11-FEB-17.