PM Schedule Start Date
Hi,
I have an issue while defining PM Schedule, I need to reschedule Schedule Start dates whenever any manual work order for the same activity is created.
For Example:
I create PM Schedule for an activity for a fixed interval of 15 days.
Forecast Window showing work orders dates as follows:
1-JAN-17
16-JAN-17
31-JAN-17
Now if any work order is created on 10-JAN-17, it should reschedule next work orders schedule start dates
after 10-JAN-17, Next work order schedule start date should be 26-JAN-17, 11-FEB-17.
Regards,
Abdul Wasi