Discrete Job Completion Date

edited Feb 5, 2018 4:02AM in Discrete Manufacturing - EBS (MOSC) 7 commentsAnswered

Hi,

We are using Oracle EBS R12.  Current issue is encountered in Work in Process module related to the calculation of discrete job completion date.  See example below. 

I have 3 operations in BOM routing, say the sequence is,

Op 1: 1 hour per item

Op 2: 0.5 hour per item

Op 3: 2 hour per item

All three operations are attached to different resource with assigned unit = 1 with 8 hours working shift (non 24-hour).  Assume that working hours is 08:00 to 17:00, Monday to Friday. 

When creating a discrete job of quantity 10, I would expect operation dates to be,

Op 1: FUSD = 11-Jan-18 08:00, FUCD = 11-Jan-18 09:00, LUSD = 12-Jan-18 09:00, LUCD = 12-Jan-18 10:00

Op 2:

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center