Assigning Scheduled Resource to a Task

edited Jan 21, 2018 11:54PM in Projects - EBS (MOSC) 3 commentsAnswered ✓

Hi,

I want to assign a scheduled resource at Project level to its task.

1. Created a requirement at project level.

2. Filled requirement. Resource is approved. Scheduling status is 'Confirmed', approval status is 'Approved'.

3. Now for assignment to task, in the workplan tab, Task> Update Task > Add Roles > Add Planning Resources

     Team role is now available at Task.

But if "Create Team Roles" button is clicked, it shows up just added planning resource. Then it creates a new requirement in Resource workbench.

Question: Isn't it wrong that new requirement is being created even though team role is approved? Or am I doing something wrong?

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center