Difference Between Simulated Net Added & Simulated Net Total fields of P30026
Hello,
I am having 2 items. 1st one is WWT001 & the another one is DIS001. Item WWT001 is used in the BOM of DIS001 item at Operation Seq-40.
Now my question is, i have done the roll up & can see the Simulated Net Added & Simulated Net total fields for 1st Item WWT001 is same for B1 & B3 cost, whereas it is different for DIS001 item. Refer below screenshots.
Also refer below screenshot of Cost by Work center, where i can see the issue is at Operation Seq-40. (DS004 Work Center)
If i have calculate the cost manually, then i can see system is calculating the final simulated cost correctly for item, but could see simulated Total for A1 cost is less by X amount at Ope Seq-40, where as the simulated Total for B1 & B3 cost are more by the Same X amount at Ope Seq-40 as compared to Simulated Net Added. It seems some functionality or logic behind this, but i am not able to get the calculation.