Need help with defining PM schedule
Community Members,
Need help with a requirement on EAM schedule.
I'm trying to create a schedule with 3 activities A, B, C.
A and B should be done 1 year apart (starting with A) and C every 6 years and when C is done, it should suppress A and B. Basically, A and B take turns every year.So, every A is 2 years apart and same with B as well. See screenshot.Once C is complete, the new cycle starts from A but it should start after 1 year "C" was last completed.
Cycle 1:
01-Jan-2014 - A
01-Jan-2015 - B
01-Jan-2016 - A
01-Jan-2017 - B