Capture of Quanties PRoduced on a Physical Job Site thru E1 Job Cost Module
Hello,
We have finished creating a NEW JOB Budget WBS that will help capture Quantities produced on a job site.
In the example below , we have defined cost type "0997" as a line that will capture the actual qties produced from our people installing product on a job. Cost type 0998 is how many QTIES we are budgeting to complete.
By setting up the WBS in this fashion , we are hoping to get a budgeted unit cost and an actual unit cost.
My question is : Where or how is the best place/process to get the "Actual QTIES Produced/installed" into E1 ?