In Demand Processing, using RSDJ Delivery Date to calculate requested ship date.
We are using 9.2 Demand Processing.
Our customer sends only a delivery date (RSDJ) through EDI Demand Processing. In the F47173, the only populated date is delivery date. (eg. 3/9/18)
When the user runs R47171, we use the DELDATE preference to add in transit days so that we can back into a requested ship date. (eg. 3 transit days)
When the record is generated into F40R11, we now have a req ship and prom delivery date. (ex. ship 3/6/18 deliver 3/9/18)
We run R40R010 and the order and shipment are created and routed appropriately.
Our problem comes when the customer sends an add on order, with a delivery date of two days out. We run R47171, which moves the record into F40R11.