Assy Completion with directed drop MSCA
Hi,
We are a manufacturing company using Oracle ebs R12.1.3 and having discrete manufacturing, inventory, WMS as well as MSCA.
We are using from mobile application a function called: "Assy Completion w/ Directed Drop" to be able to complete DJ and do put away at the same time as LPN packing.
So we navigate to LPN Txn > Assy Completion > Assy Completion w/ Directed Drop
the problem is that to be able to use this you need to first move the DJ from op seq 10 for example "Queue" to "To Move" as otherwise quantity is not available to be transacted.
Question: Is there any way you can use this function without need to move the Job first? or is there any way to release the job so it comes into "To Move" instead of "Queue". Is there any where we can set it up or profile option or similar to avoid this step which does not add any value and just manual work for us?