Process costing
Hi,
I have followed the doc 1592230.1 for process costing.
I have one ingredient. op 10
I have 4 Co-products and the Feat% 45%, 30%, 12% and 13% op 10
the output quantity is the same as the Feat%.
the resource % is the same as the feat %
all 4 co-products are planned 100% and cost 100% from one process
when I do the cost roll-up all the Co-products have the same cost? I wonder why.
All ACQ are =1