PeopleSoft Purchasing - Lead Day / Due Date Calculation
We are on Peoplesoft Version 9.2, wondering if there is a way to omit weekends in the due date calculation. Currently if the lead days is 5 and the due date falls on a weekend, the due date is set to the next available business day. Users are asking if we can omit weekends from the calculation, so if the PO is cut on a Wednesday and the lead days are 5, instead of the due date being Monday (weekend days are included), the due date would actually be Wednesday ( so 5 business days instead of 5 calendar days).
Thoughts?
Thanks in advance.