I have question related about functionality of Landed cost recalculation process
Dear All,
I have question related about functionality of Landed cost recalculation process
we have a case related to estimated amount
that I get wrong estimated cost after running "Matches Interface Import" , "submit pending match "and "Landed cost recalculation process" requests.
for example
before running above requests : Estimated cost was 3,287.55
after that : Estimated cost become 3,167.42
but the expected result is 3,287.55
need your clarification
Steps:
1- Create PO
2- Receipt PO.
3-Create LCM Shipment.
4-Enter Estimated cost 3,287.55
5-Create AP Invoice and Match the charge.
6-Run Match Interface Import.
7-Run Submit Pending Shipment.
8-Actual cost become : 3167.42
9-Run Landed cost recalculation process request (scheduled).