Work Order Start and End end date changing

edited Apr 18, 2018 5:01AM in Value Chain Planning - EBS (MOSC) 1 commentAnswered

Scenario:

Work Order - 1234

FG - XYZ

Scheduled Start Date - 01-Apr-2018

Scheduled Completion Date - 30-Apr-2018

Operation level:

- Op-10: 01-Apr-2018 to 10-Apr-2018

- Op-20: 11-Apr-2018 to 20-Apr-2018

- Op-30: 21-Apr-2018 to 30-Apr-2018

At this stage, if we move the first operation by 10 days and new Op-10 start date becomes 11-Apr-2018, it is changing the work order header level start date also.

Issue here is - we don't want the work order header level start date to move in spite of moving the op-10 start date by 10 days.

How can we prevent the header date from changing.

Regards,

Pranit.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center