EAM PM Schedule - Wrong Dates for forecast
ello All,
Trying to create a PM schedule with three activities:
12 month - Last Service Date 01-Jan-2018
24 month - Last Service Date 01-Jan-2018
36 month - Last Service Date 01-Jan-2018
Base Interval = 365 days i.e 1 year.
See attached screenshot - When the run the program with 1 year forecast, I'm getting 26-MAR-2018 (and not 01-JAN-2019) as the suggested start date. What am I messing up? Thx.