Resource requirements on OPM work orders show as past due dates
Resource requirements on OPM work orders show as past due dates in a constrained ASCP plan. This is occurring regardless of whether the source OPM work order is firm or not. This presents a problem because the past due demand is not captured by ASCP; we are currently forced to manually update OPM batch step completion and resource usage dates to correct this. Is there a method to update the resource requirements directly in ASCP? Is it possible to have these changes updated on the OPM side to ensure ASCP’s expectations are accurately reflected on the process batch? Please provide