Client vs EPPM / TM Expected finish "time of day"

edited Feb 1, 2019 7:06PM in Primavera (MOSC) 8 commentsAnswered ✓

Good afternoon,

Testing 17.12.3 - Am I seeing this correctly or is there a setting to change? I have sent videos to Oracle Support showing the below issue.

I have a TASK using the 8:00AM to 5:00PM calendar, so for example start 04/16/18 8:00AM and finish 05/11/18 05:00PM. Updates via the client properly assign 8AM and 5PM respectively to the start and finish dates when I pick from the calendar.

However, when picking an expected finish date from the calendar via TM Activities or in the EPPM, 12:00AM rather than 05:00PM is assigned. When we F9 Schedule, the finish date is scheduled and shown as 05/

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center