For a purchase order, should the old dock date match the need by date in the PWB and the PO need by
Hi,
Note: profile "MSC: Purchase Order Dock Date Calculation Preference" = Need By Date.
After a full data collection and plan launch.
In source the PO need by date = 26-Jun-2018
In PWB the fields have the following dates for a purchase order:-
Need by date = 26-Jun
Old Dock Date = 12-Jun
I was expecting the PWB old dock date to match the PO source and PWB need by dates, so I was expected them all to be the 26-Jun.
The dates don't currently match, as the example above shows, so I am getting Schedule Out messages when I don't think there should be any!