Cost by WC
Hi,
When activating cost by WC in P3009, suppose we have 3 operation sequences in the routing. Then the B1 for ex, is detailed by sequence.
This will have the detailed costs in F300261 and the summary in F30026.
When running R31802A :
- Are we going to have a B1 by operation seq in F3102?
- Or the cost by WC does not have any impact: One B1 for all 3 operations.
thanks