Schedule Comparison does not respect advanced option selections
In schedule comparison am I normally not interested in changes to the WBS, but if I unselect this comparison in the the advanced options it has no effect, WBS differences are still reported. The problem with this is that for large projects (eg. +5000 tasks), every single task is reported as having WBS changes simply because of the different project file name.
1. is there a work around or trick to this that anyone knows?
2. Does everyone agree that a better feature would be to ignore the project file name in the comparison process?