Can we refresh WO parts list commitment ?
Hello,
Our process is:
- Generate the Work Order
- Creates a parts list
- Soft commitment only
- WO Status = 20
- Print the Work Order
- Checks availability of components
- Where possible, hard commits,
- Where not possible, leaves a soft commit against the default location
- WO Status = 40
The request I have had is around 2.c.
- A work order has been printed, and a soft commitment has remained due to a non availability.
- The component that is not available subsequently is receipted and released and becomes available.
- Is there a way to print the work orders again, such that the soft commitment is now assigned and hard committed, but the remaining commitments remain unchanged?