How to process AP Future dated payments by using Payment Manager
Hi All,
How to process AP Future dated payments by using Payment Manager
I have a requirement where User want to use Future dated payments.
Requirement is below.
1. When we make a payment, system should generate below accounting for payment after running CA program.
Dr. Liability
Cr. Future dated Payment
2. At the time of Maturity
Dr. Future Dated payment
Cr. Cash/bank Account.
Please note, We are not using Cash management to reconcile payment.
Here issue is, One payment can have many invoices and with different due dates so system will pick which date as payment Maturity date here? if we make payment through Payment batch.