Error occured when importing resource assignment from excel
Hi,
I am using P6 rel 17.12 - standalone Sqlite db.
I export resource assignment in excel contains following fields (
Activity ID | (*)Activity Status | Resource ID | Role ID | Cost Account ID | (*)Resource Type | (*)Start | (*)Finish | Budgeted Units(d) |
I Update the budgeted unit . Once I import it back to P6 It says the process is not completed successfully with the log shown hereunder.
I didnt have such problem in previous version of P6.
Appreciate if someone help me to resolve the problem.
Thanks,
Manochehr
-------------------------------------------------------------------------------
xcel Import log started : 25-Jul-18
INFO: Importing Global Data...
INFO: Importing Project Data...
INFO: Importing:
INFO: Saving: