Erroneous Planned order pegged only to safety stock even though OHQ covers SS requirements
ASCP Gurus
Please assist me in understanding why the plan is behaving this way. Sorry pics arent that good. But basically we are getting a planned order (with compression days) to satisfy the safety stock on 8/16/18. However our current OHQ is approx 15k and between forecast and dependent demand there is only approx 9400 demand add in the safety stock requirement and demand becomes 10600. So projected on hand should be 4400 after all of these demands. Lots do not expire until 2019 so no concerns there. Why is ASCP essentially ignoring the OHQ when trying to satisfy this SS requirement next week?
The 2nd pic demonstrates that immediately after planned order this item has excess inventory as there currently is no future demand forecast loaded in the system.