ASCP - Parallel Processing

edited Oct 4, 2018 11:50AM in Value Chain Planning - EBS (MOSC) 6 commentsAnswered

Hi All Experts,

We have got a requirement and need to model this in ASCP.

We can create a one big work order. THIS IS MANDATORY for some statutory purpose and we cannot split the big one work order.

But we can run the work order through multiple parallel resources.

We need to get estimated start and completion times from ASCP for this.

For example: - We can create work order for lets say 1000 units.

Lets say I can process 10 units per hour on the machine.

We have got 4 machines which do same job.

Now practically we can run 250 units on each machine and complete the work order within 2.5 hrs.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center