Anyway to have component requirements show earlier than start date of parent wip job?

edited Oct 19, 2018 2:59PM in Value Chain Planning - EBS (MOSC) 8 commentsAnswered

In ASCP options we have the Material Scheduling Method set to Operation Start Date. Our internal supply chain performance historically is at around 75% on time. Because of this we struggle from time to time with material shortages at the beginning of jobs. We are wondering if there is anyway to have planning "see" that requirement x-days prior to the start date of the parent wip job? Any and all suggestions are welcome and thanks in advance!