ETO MRP with STKT = M
Hi all
i've the following issue.
i've two different projects that have the same component in two work orders related to the the project.
the two WOs are related to a prj man items (STKT=L), but the component in common is STKT=M.
the two WO are planned in the same timing bucket (F3413)but the system propose me 2 different messages in order to satisfy the demand:the only way to consolidate them is to put the same planned date on the two WOs (of the 2 different projects).
the Planning period of the version of R3482 is correctly setupped, and also the items (component and the 2 father items)are correct.