Hi all

i've the following issue.

i've two different projects  that have the same component in two work orders related to the the project.

the two WOs are related to a prj man items (STKT=L), but the component in common is STKT=M.

the two WO are planned in the same timing bucket (F3413)but the system propose me 2 different messages in order to satisfy the demand:the only way to consolidate them is to put the same planned date on the two WOs (of the 2 different projects).

the Planning period of the version of R3482 is correctly setupped, and also the items (component and the 2 father items)are correct.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center