Cost/Event or Event/Event?

edited Oct 2, 2018 5:01AM in Projects - EBS (MOSC) 4 commentsAnswered

Dear All,

We have to find out which extension to customize/use standard to achieve revenue accrual calculation to suit our business needs.

A)Please suggest should we use percent spent (cost/event) or Event/Event extension.

Here is our logic, thanks for reading in advance.

     A1) If Contract total is > 1 Million then it is "ClassP" project, else it is "class NP" project.

          For "ClassP" project, we will assess a risk % and add it to original baselined cost budget, which usually increases cost budget from previous baseline.

               We call it "Revised cost budgetP"
  

          For class NP project, no change in original baselined budget.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center