Hello! Question about CA_BI_INTFC not updating BI_DISTRIB_STATUS to ‘W” in PROJ_RESOURCE
We ran the billing process (cost collection/interface) and can see the priced rows in PROJ_RESOURCE. The jobs ran to success. However, the rows were never turned into worksheets, and therefore no worksheet was created for this contract/project to approve or delete. The other hint that something was wrong was that the Bill plan status was in a “pending” status rather than “In progress” or “Ready” status. After investigating, we saw that the “Bill to contact” in the customer information was missing on the Bill Plan for this contract. After creating a Bill to customer contact, then rerunning the interfaces, the