Work order routing
Hi,
For an item, I have to issue 1.24 KG of component items to get 1 KG of FG item. Remaining quantity is not a scrap. It is getting vaporized.
I am already considering this vaporized quantity in BoM and added needed quantity to get total 1.24 component items Weight and to get 1 KF of FG after vaporization.
My question here is as I am already adding extra needed quantity in BoM itself, then is there a need to define planned yield % in Routing.