MRP Considering Unprocessed WO Messages
Hello,
I am having a query related to Unprocessed WO Messages which currently system is considering as a demand while running the MRP. Below are the details:-
1) We have entered the Forecast as a Demand for FG Items.
2) Based on this Demand MPS Suggesting multiple Messages.
3) Now as per requirement, half of the Messages are processed and firm Work Orders are created.
4) Now in Supply and demand screen, for the RM item (Which is being used to manufacture the FG Items) system showing both the Demand (Demand of Processed and Unprocessed both the messages)
5) After running MRP for RM item, system considering both the demand (Demand of Processed and Unprocessed both the messages)