Requirement on Preventive maintenance

edited Nov 16, 2018 4:00AM in Enterprise Asset Management - EBS (MOSC) 13 commentsAnswered

We have a total of 7 Rotors. There are 4 rotors labelled R4, R5, R6 and R7 in the 2 boxes -BOXA and BOXB. The other 2 are on the top left corner labelled 1 and 2 in the HE box . The 7th one is in the  Stores yard. (We can keep the 7th Rotor aside for the moment)

Currently, these assets are not defined in eAM.

Each rotor in the box  BOXA and BOXB should run on a 22 week PM cycle of a Minor and Major Overhaul. @Every 11 weeks two rotors will go out of the box to go for servicing to HE (Top left box), and  at the same time 2 will return from HE into the BOXA/ BOXB box, replacing the rotors that exited.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center