ADOP Cutover - Best practise on scheduled requests/alerts
We are on EBS 12.2 and an issue came up recently during technology stack patching in anticipation of HRMS patching. Staff reported that a scheduled alert did not run as it was scheduled to run while the application was down during adop cutover. Staff are requesting that when we patch, we check to see if any scheduled concurrent requests or alerts were in the timeframe causing them to be missed.
Has anyone else addressed this issue? What is the best practice for those patching to ensure scheduled jobs don't get skipped or fail because of the patching timeframe?
Lydia