We have a need to take one purchased part and send it out for OSP to make it into two different part numbers.  I need to know how to do that with a BOM and still maintain cost roll up.  Here is the example:

  1. We buy part X1234 from one source.
  2. We create a work order for two different jobs to drive OSP for parts Z987 and T555.
  3. We send part X1234 out to the OSP source.
  4. The OSP source cuts and machines the one part into two different parts, Z987 and T555.
  5. The OSP source sends us the two parts and invoices us for the two different parts.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center