Hi,

Can CTP be used in case of an Unconstrained ASCP plans? (for ATP based on plan o/p)

As Unconstrained Plan wont take into consideration the resource & material capacities & the results out of ATP/CTP inquiry will be based on the unconstrained plan o/p, will it honor the capacities that are used in the routings?

The requirement is to enable CTP for an unconstrained ASCP plan and it should consider the resource capacity constraints while scheduling the Demands.