We are using 9.1. The issue happens in the below scenario,

  • This happens when the SO is at status be 555 -560.
  • Now when the report R42950 runs, it picks the SO with the status 555-560 and process it (not yet completed).
  • If the user performs Ship confirmation now, the status will be moved to 560-620.
  • When the report R42950 completes, it puts back the status 555-560 (the initial status when the SO was picked by the report).
  • That is the issue happens when the Ship confirmation is done before the scheduler report R42950 is completed.
  • Hence the order available for ship confirm again and the inventory is reduced twice.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center