Hi All

Am new to OPM functionality have worked extensively with discrete, so forgive my basic questions.

In discrete I can set up an operation to have the same resource more than once as a basis of lot and item which is great for adding in a setup or clean up step.  In OPM per operation can I only add the resource once?

The reason I am asking is that I want to do resource alternates depending on the capacity but if I have the resource is two operations (one for running and one for cleaning), I am finding that operation 1 uses the alt resource and then operation 2 uses the primary, which you can probably guess makes no sense at all. So my ultimate requirement is to use alt resource on both operations or not at all.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center