ASCP with Project Manufacturing Environment
Hello Gurus,
We are currently working for a new requirement and below is the requirement.
1. An assembly CC1 is made for commercial customer CCust which is made using non-project manufacturing
2. An assembly GG1 is made for a specific group GCust which is made using project manufacturing
a. Both CC1 and GG1 has a common item AA1
Case 1:
1. Demand for AA1 for making GG1 – 10
2. Common Inventory which was purchased for making CC1 has 5 quanties of AA1
3. There is an outstanding PO for a quantity of 3 for AA1
4. For the demand for AA1 for making GG1, Does planning engine take into account the quantity of 5 that is in Common Inventory and PO for 3 quantity?