The Site Server Planning Guide for the M4000 server lists this for power requirements:

edited Feb 27, 2019 9:41AM in SPARC M-series servers (MOSC) 1 commentAnswered ✓

The Site Server Planning Guide for the M4000 server lists this for power requirements:

24.0A at 100–127 VAC (12A/cord)

12.0A at 200–240 VAC (12A/cord)

The first line makes sense. 24A total, 12A per cord.
I don't understand the second line. If the total amperage is 12A and there are two power cords, shouldn't it be 6A per cord? The only time it should be 12A/cord is if there's only one power supply.
Am I misunderstanding something?
I'm looking to relocate a few M4000 servers. At the same time, I plan to change from 110V to 220V. (The power supplies are only considered redundant if they're plugged in to 220.)

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center