Flexible Accounting in Maintenance Issue
Hi All,
I have some problem about flexible accounting in maintenance issue process. I need to do issue with the same document type is IM and to different subsidiary account. I have defined the issues below.
1- DMAAI- 4124 is defined like below.
2- Category codes defined in work order. It's selected in the work order is 1021436
Phase - WR01
Category 02 - WR02
3- Flexible account set - up is defined for document type is "IM" and DMAAI is "4124".
4- Flexible applications was created for P31113 in P16902.
After all this set-up, when I try to do issue in P31113, I get error like below. It seems system doesn't see flexible accounting set-up. Could you please help me? Is it possible to use this set-up for maintenance issue?