Work order status change problem for Process item
HI All,
Can anybody help me out on this issue of Work Order Status movement.
In JDE 9.1.5 we are using Process & Discrete manufacturing, superbackflush completion and after completion it goes to receipt routing and then to stock. So ideally after superbackflush my status should move to 80 (as it is moving to receipt routing) and after moving from receipt routing the status should change to 95. But in my case after moving from receipt routing the status is not changing to 95 even after moving complete quantity. The status stays in 80. But for discrete items the status is changing as desired (80 to 95 after moving from receipt routing)