Hello,

I am having a query in an Application Work Center Load Review P3313 after running the R3382 RCCP Generation.

I have updated Forecast for an Item MF001 as below:- (Lead Time -5 Days)

14th Jan-100 Qty

21st Jan 200 Qty.

So after running the MPS, system suggested a WO messages with Start Date as 7th and 14th of Jan with Qty as 100 and 200 respectively. (Based on Lead time and Sat/Sun as Holiday)

Total Hours Available Per Day after running the Resource Unit Program is 16 Hours per Day.

Work Center is with Prime Load= Machine Hours Only which are 2 Hours defined in Routing.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center