PM Schedule not generating workorder
Hi,
We have defined a PM schedule as shown below, with base interval as 200,000 and last service reading as 2844679 and the current meter reading is 3083839. Based on the last service reading and current meter reading the base interval of 200,000 is met ( 3083839 - 2844679 = 239,160) the PM schedule should have generated a workorder for today since the base interval is met.
But when we try to simulate the workorder from the maintenance workbench it does not simulate any workorders with a horizon of 1.
When we try to increase the horizon by few more days until we see a simulated work order, it was around 550 days horizon it simulated a workorder for 26-JUN-2020