I have a WO with FG lead time of 1 day (requested Monday 1/14/19).
MFG working calendar is set for 1/12 and 1/13 as non working (Sat and Sun).
The WO has Purchased RM with LT also 1 day.
Run R3482, the supply and demand show the demand for the RM on 1/13/19 instead of the 1/11/19.
Any set up need to be checked?