Cancelled AP invoice costs not reflected in Projects
Hi,
We are using R12.1.3. We have an issue where, for example, an AP invoice is created, validated and accounted, and is linked to a Project in PA.
The cost for the AP Invoice hit GL fine via AP Create Accounting.
We have a PA overnight Request Set running, containing the following jobs:
- PRC: Interface Supplier Costs
- PRC: Distribute Usage and Miscellaneous Costs
- PRC: Distribute Supplier Cost Adjustments
- PRC: Create and Distribute Burden Transactions
- PRC: Generate Draft Revenue for a Range of Projects
- PRC: Generate Revenue Accounting Events
- PRC: Generate Cost Accounting Events
- PRC: Create Accounting
- PRC: Update Project Summary Amounts